CDBG-MIT Proposed Activity in a Floodplain

**Click here for the SANTA FE ENVIRONMENTAL REVIEW RECORD (ERR) 

COMBINED NOTICE OF FINDING OF NO SIGNIFICANT IMPACT

AND INTENT TO REQUEST RELEASE OF FUNDS

Date of Notice Posting: July 25, 2024

Project Name: Santa Fe - 24-065-037-E529-street

Responsible Entity: City of Santa Fe

State/Local Identifier: 24-065-037-E529  / B-18-DP-48-0002

Contact:

City of Santa Fe City Hall

12002 State Hwy 6

PO Box 950

Santa Fe, Texas 77510

(409) 925-6412

athomas@santafetx.gov

These notices shall satisfy two separate but related procedural requirements for activities to be undertaken by the City of Santa Fe.

REQUEST FOR RELEASE OF FUNDS

On or about August 14, 2024 the City of Santa Fe, will submit a request to the General Land Office (GLO) for the release of Community Development Block Grant Mitigation (CDBG-MIT) funds appropriated under the Supplemental Appropriations for Disaster Relief Requirements Act, 2018 (Pub. L. 115-123), as amended to undertake a project known as Santa Fe - 24-065-037-E529-street, 24-065-037-E529  / B-18-DP-48-0002 for the purpose of improving sections of roadway within the City to help ensure safe vehicular movement in the area.

Project Location:

All work will occur in the City of Santa Fe, Galveston County, Texas at the following locations:

Ave. M from Hwy 6 to approximately 1,233 LF south of 24th St.

Ave L from 18th St. to 25th St.

  • 18th St. from Ave L to Hwy 646
  • 13th St. from Main St. to Ave H
  • 21st St. from FM 646 to Ave L
  • 22nd St. from Ave. L to Ave. M
  • 22nd St. from Ave. L to FM 646
  • 23rd St. from Ave M east 985 LF to end
  • 24th St. from Ave. L to FM 646
  • Ave K from 22nd St. to 25th St.
  • 17th St. from Ave I to Ave H
  • Ave H from Hwy 6 to 13th St.
  • 23rd St. from FM 646 to Ave L
  • 24th St. from Ave. L to Ave M
  • 16th St. from Ave. H to Main St.
  • 12th St. from Ave. L to Main St.
  • 18th St. from Ave. L to Ave M
  • Mulberry from 18th St. south 848 LF to end
  • Main St. from Hwy 6 to 10th St.
  • 16th St. from Main St. to Ave. H

Description of the Proposed Project [24 CFR 50.12 & 58.32; 40 CFR 1508.25]:

Subrecipient shall rehabilitate current roadways, which includes a full depth repair finished with a final surface of asphalt, and complete associated appurtenances.

Project forecast cost $2,743,700.00 and will be paid for with $2,743,700.00 in HUD CDBG-MIT grant funds administered by the General Land Office.

Project Issues: Floodplain Management and Historic Preservation: A full, detailed list of mitigation measures can be found in the Environmental Review Record.

Project Size and Beneficiaries

The total area of disturbance will be 14.2 acres and will impact 598 persons. Of those persons,

391 or  (65.38%) are of low to moderate income.

FINDING OF NO SIGNIFICANT IMPACT

The City of Santa Fe has determined that the project will have no significant impact on the human environment.  Therefore, an Environmental Impact Statement under the National Environmental Policy Act of 1969 (NEPA) is not required.  Additional project information is contained in the Environmental Review Record (ERR) on file at the City of Santa Fe City Hall

12002 State Hwy 6, PO Box 950, Santa Fe, Texas and may be examined or copied weekdays 9 A.M to  4 P.M.

PUBLIC COMMENTS

Any individual, group, or agency may submit written comments on the ERR to the City of Santa Fe City Hall, 12002 State Hwy 6, PO Box 950, Santa Fe, Texas 77510 and athomas@santafetx.gov. All comments received by August 13, 2024 or within eighteen (18) days following this posting (whichever is later) will be considered by the City of Santa Fe prior to authorizing submission of a request for release of funds.  Comments should specify which part of this Notice they are addressing.

ENVIRONMENTAL CERTIFICATION

The City of Santa Fe certifies to GLO that Alun Thomas, in their capacity as City Manager, consents to accept the jurisdiction of the Federal Courts if an action is brought to enforce responsibilities in relation to the environmental review process and that these responsibilities have been satisfied.  GLO’s approval of the certification satisfies its responsibilities under NEPA and related laws and authorities and allows the City of Santa Fe to use Program funds.

OBJECTIONS TO RELEASE OF FUNDS

GLO will accept objections to its release of funds and the City of Santa Fe’s certification for a period of fifteen days following the anticipated submission date or its actual receipt of the request (whichever is later) only if they are on one of the following bases: (a) the certification was not executed by the Certifying Officer of the City of Santa Fe; (b) the City of Santa Fe has omitted a step or failed to make a decision or finding required by HUD regulations at 24 CFR part 58; (c) the grant recipient or other participants in the development process have committed funds, incurred costs or undertaken activities not authorized by 24 CFR Part 58 before approval of a release of funds by GLO; or (d) another Federal agency acting pursuant to 40 CFR Part 1504 has submitted a written finding that the project is unsatisfactory from the standpoint of environmental quality.  Objections must be prepared and submitted in accordance with the required procedures (24 CFR Part 58, Sec. 58.76) and shall be addressed to Heather Lagrone, Texas General Land Office, PO Box 12873, Austin, TX 78711-2873, env.reviews@recovery.texas.gov.  Potential objectors should contact GLO to verify the actual last day of the objection period.

Alun Thomas, City Manager


AVISO COMBINADO DE CONSULTA DE NO IMPACTO SIGNIFICATIVO

E INTENCIÓN DE SOLICITAR LIBERACIÓN DE FONDOS

Fecha de publicación del aviso: 25 de julio de 2024

Nombre del Proyecto: Santa Fe - 24-065-037-E529-calle

Entidad Responsable: Ciudad de Santa Fe

Identificador estatal/local: 24-065-037-E529 / B-18-DP-48-0002

Contacto:

Ayuntamiento de la ciudad de Santa Fe

12002 Carretera estatal 6

Apartado postal 950

Santa Fe, Texas 77510

(409) 925-6412

athomas@santafetx.gov

Estos avisos deberán satisfacer dos requisitos procesales separados pero relacionados para las actividades que realizará el Ciudad de Santa Fe.

SOLICITUD DE LIBERACIÓN DE FONDOS

En ó sobre 14 de agosto de 2024 la ciudad de Santa Fe, presentará una solicitud a la Oficina General de Tierras (GLO) para la liberación de los fondos de Mitigación de Subvenciones en Bloque para el Desarrollo Comunitario (CDBG-MIT) asignados en virtud de la Ley de Asignaciones Suplementarias para Requisitos de Ayuda en Casos de Desastre de 2018 (Pub. L. 115-123), como modificado para emprender un proyecto conocido como Santa Fe - calle 24-065-037-E529, 24-065-037-E529 / B-18-DP-48-0002 a fin de mejorar secciones de carreteras dentro de la ciudad para ayudar a garantizar el movimiento vehicular seguro en el área.

Localización del proyecto:

Todo el trabajo se realizará en la ciudad de Santa Fe, condado de Galveston, Texas, en las siguientes ubicaciones:

Ave. M desde la autopista 6 hasta aproximadamente 1233 LF al sur de 24th St.

Ave L desde la calle 18 hasta la calle 25.

  • 18th St. desde Ave L hasta Hwy 646
  • 13th St. desde Main St. hasta Ave H
  • 21st St. desde FM 646 hasta Ave L
  • Calle 22 desde Ave. L hasta Ave. M
  • Calle 22 desde Ave. L hasta FM 646
  • 23rd St. desde Ave M este 985 LF hasta el final
  • Calle 24 desde Ave. L hasta FM 646
  • Ave K desde la calle 22 hasta la calle 25.
  • 17th St. desde Ave I hasta Ave H
  • Ave H desde la autopista 6 hasta la calle 13.
  • 23rd St. desde FM 646 hasta Ave L
  • Calle 24 desde Ave. L hasta Ave M
  • 16th St. desde Ave. H hasta Main St.
  • 12th St. desde Ave. L hasta Main St.
  • Calle 18 desde Ave. L hasta Ave M
  • Mulberry desde 18th St. sur 848 LF hasta el final
  • Main St. desde la autopista 6 hasta la 10th St.
  • 16th St. desde Main St. hasta Ave. H

Descripción del proyecto propuesto [24 CFR 50.12 y 58.32; 40 CFR 1508.25]:

El subreceptor rehabilitará las carreteras actuales, lo que incluye una reparación en profundidad completa terminada con una superficie final de asfalto y accesorios asociados completos.

Costo de previsión del proyecto $2,743,700.00 y se pagará con $2,743,700.00 en fondos de subvención HUD CDBG-MIT administrados por la Oficina General de Tierras.

Problemas del proyecto: Gestión de llanuras aluviales y preservación histórica: se puede encontrar una lista completa y detallada de medidas de mitigación en el Registro de revisión ambiental.

Tamaño del proyecto y beneficiarios

El área total de perturbación será de 14,2 acres y afectará a 598 personas. De esas personas,

391 o (65,38%) son de ingresos bajos a moderados.

HALLAZGO DE NO IMPACTO SIGNIFICATIVO

La ciudad de Santa Fe ha determinado que el proyecto no tendrá ningún impacto significativo en el medio ambiente humano.  Por lo tanto, no se requiere una Declaración de Impacto Ambiental según la Ley de Política Ambiental Nacional de 1969 (NEPA).  Información adicional del proyecto está contenida en el Registro de Revisión Ambiental (ERR) archivado en el Ayuntamiento de la ciudad de Santa Fe

12002 State Hwy 6, PO Box 950, Santa Fe, Texas y se puede examinar o copiar de lunes a viernes de 9 a. m. a 4 p. m.

COMENTARIOS PÚBLICOS

Cualquier individuo, grupo o agencia puede enviar comentarios por escrito sobre la ERR a la Ayuntamiento de la Ciudad de Santa Fe, 12002 Carretera estatal 6, Apartado postal 950, Santa Fe, Texas 77510 y athomas@santafetx.gov. Todos los comentarios recibidos por 13 de agosto de 2024 o dentro de los dieciocho (18) días siguientes a esta publicación (lo que ocurra más tarde) será considerado por la Ciudad de Santa Fe antes de autorizar la presentación de una solicitud de liberación de fondos.  Los comentarios deben especificar a qué parte de este Aviso se refieren.

CERTIFICACIÓN AMBIENTAL

La Ciudad de Santa Fe certifica a GLO que Alun Thomas, en su calidad de Administrador de la ciudad, consiente en aceptar la jurisdicción de los Tribunales Federales si se inicia una acción para hacer cumplir las responsabilidades en relación con el proceso de revisión ambiental y que dichas responsabilidades han sido satisfechas.  La aprobación de la certificación por parte de GLO satisface sus responsabilidades según la NEPA y las leyes y autoridades relacionadas y permite a la Ciudad de Santa Fe utilizar los fondos del Programa.

OBJECIONES A LA LIBERACIÓN DE FONDOS

GLO aceptará objeciones a su liberación de fondos y al Ayuntamiento de Santa Fe's certificación por un período de quince días después de la fecha de presentación prevista o de la recepción real de la solicitud (lo que ocurra más tarde) solo si se basan en una de las siguientes bases: (a) la certificación no fue ejecutada por el Oficial Certificador de la Ciudad de Santa Fe; (b) la Ciudad de Santa Fe ha omitido un paso o no ha tomado una decisión o hallazgo requerido por las regulaciones del HUD en 24 CFR parte 58; (c) el beneficiario de la subvención u otros participantes en el proceso de desarrollo han comprometido fondos, incurrido en costos o realizado actividades no autorizadas por 24 CFR Parte 58 antes de la aprobación de una liberación de fondos por parte de GLO; o (d) otra agencia federal que actúa de conformidad con 40 CFR Parte 1504 ha presentado una conclusión por escrito de que el proyecto es insatisfactorio desde el punto de vista de la calidad ambiental.  Las objeciones deben prepararse y presentarse de acuerdo con los procedimientos requeridos (24 CFR Parte 58, Sec. 58.76) y deben dirigirse a Heather Lagrone, Texas General Land Office, PO Box 12873, Austin, TX 78711-2873, env.reviews@recovery.texas.gov.  Los posibles objetores deben comunicarse con GLO para verificar el último día real del período de objeción.

Alun Thomas, administrador de la ciudad



Final Notice and Public Explanation of a Proposed Activity in a Floodplain

To:  All interested Agencies, Groups and Individuals

This is to give notice that the City of  Santa Fe has conducted an evaluation as required by Executive Order 11988, in accordance with HUD regulations at 24 CFR 55.20 Subpart C Procedures for Making Determinations on Floodplain Management.  The activity is funded under the HUD CDBG Disaster Recovery Program under #24-065-037-E529  / B-18-DP-48-0002, project name: Santa Fe - 24-065-037-E529-street.

Project Location:

All work will occur in the City of Santa Fe, Galveston County, Texas at the following locations:

  • Ave. M from Hwy 6 to approximately 1,233 LF south of 24th St.
  • Ave L from 18th St. to 25th St.
  • 18th St. from Ave L to Hwy 646
  • 13th St. from Main St. to Ave H
  • 21st St. from FM 646 to Ave L
  • 22nd St. from Ave. L to Ave. M
  • 22nd St. from Ave. L to FM 646
  • 23rd St. from Ave M east 985 LF to end
  • 24th St. from Ave. L to FM 646
  • Ave K from 22nd St. to 25th St.
  • 17th St. from Ave I to Ave H
  • Ave H from Hwy 6 to 13th St.
  • 23rd St. from FM 646 to Ave L
  • 24th St. from Ave. L to Ave M
  • 16th St. from Ave. H to Main St.
  • 12th St. from Ave. L to Main St.
  • 18th St. from Ave. L to Ave M
  • Mulberry from 18th St. south 848 LF to end
  • Main St. from Hwy 6 to 10th St.
  • 16th St. from Main St. to Ave. H

Description of the Proposed Project [24 CFR 50.12 & 58.32; 40 CFR 1508.25]:

Subrecipient shall rehabilitate current roadways, which includes a full depth repair finished with

a final surface of asphalt, and complete associated appurtenances.

FLOODPLAIN

According to the FFRMS CISA Report, the project is in the FFRMS floodplain. According to FEMA floodplain map #48167C0380G (Effective Date 8/15/19), the  majority of the project is located in Zone X (Area of minimal risk of flooding) and a few sections of the project are located in Zone X (0.2% Annual Chance Flood Hazard, Areas of 1% annual chance flood with average depth less than one foot or with drainage areas of less than one square mile.) The project is not a critical action. Area of Disturbance: 13.2 acres

Natural Values of the Floodplain and Floodway:  

The natural resources of the floodplain include water, biological, and societal resources. The proposed project will have minimal impacts to the floodplains because appropriate mitigation will be in place.

The City of  Santa Fe has considered the following alternatives and mitigation measures to be taken to minimize adverse impacts and to restore and preserve natural and beneficial values:

  1. Do work only outside the floodplains. Completing the project without disturbing any floodplains is not possible.  (Not Viable)
  1. Obtain a Letter of Map Amendment (LOMA) or Letter of Map Revision (LOMR). - It was determined that neither a LOMA nor a LOMR was likely nor practical for the project area. (Not Viable)
  1. Other infrastructure considered. - After considering other potential projects in the City, it was determined that of the eligible projects, this project was of the highest priority. (Not Viable)
  1. No Action or Alternative Actions that Serve the Same Purpose. - Portions of the street system are inadequate and must be addressed to prevent public health hazards. (Not Viable)

Mitigation measures to be taken to minimize adverse impacts and to restore and preserve natural and beneficial values:

  1. Preserving Property: Project designs should, to the best extent possible, incorporate measures to reduce the risk of damage to the new infrastructure via a flood.
  2. Preserving Natural Values and Minimizing Impacts: After construction is completed, the disturbed area will need to be immediately re-vegetated with native grasses. Only native plants are to be used in the floodplain and on the site. 
  3. Deposition and excavation of materials will need to be performed in such a manner that erosion and sedimentation will be controlled.
  4. Precautions will need to be taken in the handling of fuels or other hazardous materials to prevent discharge or spillage resulting in lower groundwater quality. 
  5. Erosion control measures such as hay bales or silt screen barriers will need to be implemented and maintained during construction as required.
  6. The project engineer will need to incorporate best management practices into the specifications and plans.

Date of any final or conditional LOMR’s or LOMA’s from FEMA: None requested.

The City of  Santa Fe will ensure applicable state and local floodplain protection procedures are followed. The City of  Santa Fe has reevaluated the alternatives to building in the floodplain and has determined that it has no practicable alternative.  Environmental files that document compliance with steps 3 through 6 of Executive Order 11988, are available for public inspection, review and copying upon request at the times and location delineated in the last paragraph of this notice for receipt of comments. 

There are three primary purposes for this notice.  First, people who may be affected by activities in floodplains and those who have an interest in the protection of the natural environment should be given an opportunity to express their concerns and provide information about these areas. Second, an adequate public notice program can be an important public educational tool. The dissemination of information and request for public comment about floodplains can facilitate and enhance Federal efforts to reduce the risks and impacts associated with the occupancy and modification of these special areas. Third, as a matter of fairness, when the Federal government determines it will participate in actions taking place in floodplains, it must inform those who may be put at greater or continued risk.

Written comments must be received by the City of  Santa Fe at the following address on or before July 19, 2024, a minimum 7 calendar day comment period will begin the day after the publication and end on the 8th day after the publication:  City of Santa Fe City Hall, 12002 State Hwy 6, Santa Fe, Texas 77510 and (409) 925-6412. A full description of the project may also be reviewed from 9:00 am to 5:00 pm from the previously mentioned address. Comments may also be submitted via email at todd@texasenvironmentals.com.

Date: July 11, 2024


Aviso final y explicación pública de una actividad propuesta en

una llanura aluvial

Para: Todas las agencias interesadas, Grupos e individuos

Esto es para dar aviso de que el ciudad de Santa Fe ha realizado una evaluación según lo requerido por el Ejecutivo Orden 11988, en conformidad con las regulaciones del HUD en 24 CFR 55.20 Subparte C Procedimientos para tomar determinaciones sobre llanuras aluviales Gestión.  La actividad está financiada por el Programa de recuperación de desastres CDBG de HUD bajo #24-065-037-E529/ B-18-DP-48-0002, nombre del proyecto: Santa Fe - calle 24-065-037-E529.

Localización del proyecto:

Todo el trabajo se realizará en la ciudad de Santa Fe, condado de Galveston, Texas, en las siguientes ubicaciones:

  • Ave. M desde la autopista 6 hasta aproximadamente 1233 LF al sur de 24th St.
  • Ave L desde la calle 18 hasta la calle 25.
  • 18th St. desde Ave L hasta Hwy 646
  • 13th St. desde Main St. hasta Ave H
  • 21st St. desde FM 646 hasta Ave L
  • Calle 22 desde Ave. L hasta Ave. M
  • Calle 22 desde Ave. L hasta FM 646
  • 23rd St. desde Ave M este 985 LF hasta el final
  • Calle 24 desde Ave. L hasta FM 646
  • Ave K desde la calle 22 hasta la calle 25.
  • 17th St. desde Ave I hasta Ave H
  • Ave H desde la autopista 6 hasta la calle 13.
  • 23rd St. desde FM 646 hasta Ave L
  • Calle 24 desde Ave. L hasta Ave M
  • 16th St. desde Ave. H hasta Main St.
  • 12th St. desde Ave. L hasta Main St.
  • Calle 18 desde Ave. L hasta Ave M
  • Mulberry desde 18th St. sur 848 LF hasta el final
  • Main St. desde la autopista 6 hasta la 10th St.
  • 16th St. desde Main St. hasta Ave. H

Descripción del proyecto propuesto [24 CFR 50.12 y 58.32; 40 CRF 1508.25]:

El subreceptor rehabilitará las carreteras actuales, lo que incluye una reparación profunda terminada con

una superficie final de asfalto, y accesorios asociados completos.

Llanura de inundación

Según el informe FFRMS CISA, el proyecto se encuentra en la llanura aluvial de FFRMS. Según el mapa de llanura aluvial de FEMA #48167C0380G (Fecha de entrada en vigor 15/8/19), la mayor parte del proyecto está ubicado en la Zona X (Área de riesgo mínimo de inundación) y algunas secciones del proyecto están ubicadas en la Zona X (0.2% Peligro de inundación con probabilidad anual, áreas con una probabilidad de inundación anual del 1 % con una profundidad promedio inferior a un pie o con áreas de drenaje de menos de una milla cuadrada). El proyecto no es una acción crítica. Área de perturbación: 13,2 acres

Valores naturales de la llanura aluvial y el cauce aluvial:  

Los recursos naturales de la llanura aluvial incluyen recursos hídricos, biológicos y sociales. El proyecto propuesto tendrá impactos mínimos en las llanuras aluviales porque se implementará la mitigación adecuada.

El ciudad de santa fe ha considerado las siguientes alternativas y medidas de mitigación a tomar para minimizar los impactos adversos y restaurar y preservar los valores naturales y beneficiosos:

  1. Trabaje sólo fuera de las llanuras aluviales. No es posible completar el proyecto sin alterar las llanuras aluviales.  (No es viable)
  1. Obtenga una Carta de Enmienda del Mapa (LOMA) o una Carta de Revisión del Mapa (LOMR)). - Se determinó que ni una LOMA ni una LOMR eran probables ni prácticas para el área del proyecto. (No es viable)
  1. Otras infraestructuras consideradas. - Después de considerar otros proyectos potenciales en la Ciudad, se determinó que de los proyectos elegibles, este era el de mayor prioridad. (No es viable)
  1. Ninguna acción o acciones alternativas que sirvan el mismo propósito. - Partes del sistema de calles son inadecuadas y deben abordarse para prevenir riesgos para la salud pública. (No es viable)

METROMedidas de mitigación que se deben tomar para minimizar los impactos adversos y restaurar y preservar los valores naturales y beneficiosos:

  1. Preservación de la propiedad: Los diseños de los proyectos deben, en la mejor medida posible, incorporar medidas para reducir el riesgo de daños a la nueva infraestructura a través de una inundación.
  2. Preservar los valores naturales y minimizar los impactos: una vez finalizada la construcción, será necesario revegetar inmediatamente el área perturbada con pastos nativos. En la llanura aluvial y en el lugar sólo se utilizarán plantas autóctonas. 
  3. La deposición y excavación de materiales deberá realizarse de tal manera que se controle la erosión y la sedimentación.
  4. Será necesario tomar precauciones en el manejo de combustibles u otros materiales peligrosos para evitar descargas o derrames que resulten en una menor calidad del agua subterránea. 
  5. Será necesario implementar y mantener durante la construcción medidas de control de la erosión, como fardos de heno o barreras de pantalla de sedimento, según sea necesario.
  6. El ingeniero del proyecto deberá incorporar las mejores prácticas de gestión en las especificaciones y planes.

Dfecha de cualquier LOMR o LOMA final o condicional de FEMA: Ninguno solicitado.

El ciudad de santa fe asegurará que sea aplicable Se siguen los procedimientos estatales y locales de protección de llanuras aluviales.d. El ciudad de santa fe tiene reevaluó las alternativas a la construcción en la llanura aluvial y ha determinado que no tiene otra alternativa viable.  Los archivos ambientales que documentan el cumplimiento de los pasos 3 a 6 de la Orden Ejecutiva 11988 están disponibles para inspección, revisión y copia del público previa solicitud en los horarios y lugares delineados en el último párrafo de este aviso para la recepción de comentarios. 

Hay tres propósitos principales para este aviso.  En primer lugar, se debe dar a las personas que puedan verse afectadas por las actividades en las llanuras aluviales y a aquellos que tengan interés en la protección del medio ambiente natural la oportunidad de expresar sus preocupaciones y proporcionar información sobre estas áreas. En segundo lugar, un programa adecuado de avisos públicos puede ser una importante herramienta educativa pública. La difusión de información y la solicitud de comentarios públicos sobre las llanuras aluviales pueden facilitar y mejorar los esfuerzos federales para reducir los riesgos e impactos asociados con la ocupación y modificación de estas áreas especiales. En tercer lugar, como cuestión de justicia, cuando el gobierno federal determine que participará en acciones que se lleven a cabo en la llanura aluvials, debe informar a quienes puedan correr un riesgo mayor o continuo.

Los comentarios escritos deben ser recibidos por el ciudad de santa fe A la siguiente dirección en o antes de julio 19, 2024, un período mínimo de comentarios de 7 días calendario comenzará el día después de la publicación y finalizará el día 8th día después de la publicación:  Ayuntamiento de la ciudad de Santa Fe, 12002 State Hwy 6, Santa Fe, Texas 77510 y (409) 925-6412. También se podrá revisar una descripción completa del proyecto de 9:00 am a 5:00 pm desde la dirección mencionada anteriormente. Los comentarios también pueden enviarse por correo electrónico a todd@texasenvironmentals.com.

Fecha: 11 de julio, 2024


Early Notice and Public Review of a Proposed Activity in a Floodplain

This is to give notice that the City of Santa Fe has determined that the following proposed action under the Community Development Block Grant - Disaster Recovery Program administered by the Texas General Land Office – U.S. Department of Housing and Urban Development’s Community Development Block Grant Mitigation (CDBG-MIT) and Santa Fe - 24-065-037-E529-street, 24-065-037-E529  / B-18-DP-48-0002, is located in a floodplain and the City of Santa Fe will be identifying and evaluating practicable alternatives to locating the action in the floodplain and the potential impacts on the floodplain from the proposed action, as required by Executive Order 11988, in accordance with HUD regulations at 24 CFR 55.20 Subpart C Procedures for Making Determinations on Protection of Floodplains.

Project Location:

All work will occur in the City of Santa Fe, Galveston County, Texas at the following locations:

  • Ave. M from Hwy 6 to approximately 1,233 LF south of 24th St.
  • Ave L from 18th St. to 25th St.
  • 18th St. from Ave L to Hwy 646
  • 13th St. from Main St. to Ave H
  • 21st St. from FM 646 to Ave L
  • 22nd St. from Ave. L to Ave. M
  • 22nd St. from Ave. L to FM 646
  • 23rd St. from Ave M east 985 LF to end
  • 24th St. from Ave. L to FM 646
  • Ave K from 22nd St. to 25th St.
  • 17th St. from Ave I to Ave H
  • Ave H from Hwy 6 to 13th St.
  • 23rd St. from FM 646 to Ave L
  • 24th St. from Ave. L to Ave M
  • 16th St. from Ave. H to Main St.
  • 12th St. from Ave. L to Main St.
  • 18th St. from Ave. L to Ave M
  • Mulberry from 18th St. south 848 LF to end
  • Main St. from Hwy 6 to 10th St.
  • 16th St. from Main St. to Ave. H

Description of the Proposed Project [24 CFR 50.12 & 58.32; 40 CFR 1508.25]:

Subrecipient shall rehabilitate current roadways, which includes a full depth repair finished with

a final surface of asphalt, and complete associated appurtenances.

FLOODPLAIN

According to the FFSST, the project is in the FFRMS floodplain.

According to FEMA floodplain map #48167C0380G (Effective Date 8/15/19), the  majority of the project is located in Zone X (Area of minimal risk of flooding) and a few sections of the project are located in Zone X (0.2% Annual Chance Flood Hazard, Areas of 1% annual chance flood with average depth less than one foot or with drainage areas of less than one square mile.)

The project is not a critical action. Area of Disturbance: 13.2 acres

Natural and beneficial values potentially adversely affected by the activity:

  1. Preventing loss of life and property as a result of flooding is the highest priority. Another flood could damage the new infrastructure.
  2. In addition to concerns for life and property, the City has considered the natural values of the floodplain.  The natural resources of the floodplain include water, biological, and societal resources. The proposed project will have minimal impacts to the floodplain because there will be minimal disturbance to the floodplain.
  3. According to consultation with the USFWS and review of the TPWD County Species List, it was concluded that the construction of the facilities will have no quantifiable impact on plant and animal life. Only native plants are to be used in the floodplain and on the site. 
  4. Societal resources should also be considered during the design process. The designs are meant to complement the natural features of the area and to offer an aesthetically pleasing structure.  The site will not have an effect on agricultural lands.

 

There are three primary purposes for this notice.  First, people who may be affected by activities in floodplains and those who have an interest in the protection of the natural environment should be given an opportunity to express their concerns and provide information about these areas. Commenters are encouraged to offer alternative sites outside of the floodplain, alternative methods to serve the same project purpose, and methods to minimize and mitigate impacts.  Second, an adequate public notice program can be an important public educational tool. The dissemination of information and request for public comment about floodplains can facilitate and enhance Federal efforts to reduce the risks and impacts associated with the occupancy and modification of these special areas. Third, as a matter of fairness, when the Federal government determines it will participate in actions taking place in floodplains, it must inform those who may be put at greater or continued risk.

Written comments must be received by the City of Santa Fe at the following address on or before July 8, 2024, City of Santa Fe City Hall, 12002 State Hwy 6, PO Box 950, Santa Fe, Texas 77510 and (409) 925-6412. A full description of the project may also be reviewed from 9:00 AM to 5:00 PM. at the address above.  Comments may also be submitted via email at todd@texasenvironmentals.com.

 

Posting Date: June 21, 2024